The Import Process Step by Step: From Sourcing to Delivery
The import process in 12 steps: classify, source, contract, domicile, pay, inspect, ship, clear customs and close the file, with a dated example and checklist.
Key takeaways
- An import runs through four phases: preparing the purchase, securing formalities and payment, production and shipping, then clearance, delivery and closing the file.
- Classify the product and check its duties and import conditions before you negotiate: they decide whether the deal is worth doing at all.
- Choose an Incoterm that gives you control of the main carriage when you can (FCA or FOB), so freight, insurance and destination charges hold no surprises.
- Complete home-country formalities such as bank domiciliation before the supplier ships, and make inspection a condition of payment.
- Prepare clearance before the vessel arrives: every day spent waiting for a document after free time ends costs demurrage.
An import is the mirror of an export, with one big difference: you pay before you see the goods, and you discover the real cost only when everything has been cleared. Between the first quote and the goods in your warehouse there are a dozen steps and as many people: the supplier, a freight forwarder, the shipping line, your bank and the supplier's bank, a customs broker, customs, and sometimes inspectors and control authorities. Each one needs the right information at the right moment.
When the steps run in the right order, the goods arrive on time, at the price you calculated, and the file closes cleanly with your bank. When one is skipped, typically shipping before the formalities are done, paying before inspecting, or leaving the documents to the last minute, the cost appears later as demurrage, a blocked bank file or a container of goods you cannot use.
This lesson walks you through the import process in twelve steps grouped in four phases, from the buyer's side, for a sea shipment. A dated example, a filling machine bought in Italy by a dairy in Béjaïa, shows how the steps fit together.
Phase 1: preparing the purchase
Step 1. Define the product, classify it and check the import rules
Before you ask for prices, write down exactly what you need: specifications, standards, quantities, packaging, delivery date. Then find the product's HS code in your national tariff and check four things:
- the import duty rate and any additional levy for that tariff line and origin;
- whether the product is subject to a conformity, sanitary or phytosanitary control at the border;
- whether a licence, permit, registration or technical approval is required;
- any import ban, suspension or quota.
These answers decide whether the deal is viable. A product with a high duty or a control you cannot satisfy is not worth negotiating.
Step 2. Find and check suppliers
Identify several potential suppliers and check that each one exists, makes what it claims and can be paid safely. The method is explained in finding and vetting suppliers.
Step 3. Compare quotes on landed cost, not on price
Ask every supplier to quote on the same basis, ideally FCA or FOB at a named place under Incoterms® 2020, so you can add your own freight. Then compare the full cost of each offer delivered to your warehouse: price, freight, insurance, duties, taxes, port charges, clearance, inland transport and financing. The calculation is in import costs and the landed cost.
Step 4. Negotiate and sign the contract
Put in writing everything that protects you: precise specifications and tolerances, the standard the goods must meet, packaging and marking, delivery date and penalties for delay, inspection before shipment and its consequences, payment terms, the documents the supplier must provide, warranty, governing law and dispute resolution. A proforma invoice countersigned by both parties is enough for simple purchases; equipment and large orders deserve a full international sales contract.
Phase 2: formalities and payment
Step 5. Complete the import formalities in your country
Many countries attach formalities to each import. In Algeria, every import of goods must be domiciled with an approved bank, and under Banque d'Algérie note 01/DGC/2026 of 14 May 2026 the domiciliation must take place before the supplier ships; importers must also meet the current import-programme requirements of the Ministry of Foreign Trade. The details are in importing into Algeria. Elsewhere, you may need an importer registration, an import licence or a product approval. Never let the supplier ship before these are in place.
Step 6. Set up the payment
Put in place the payment method agreed in the contract: a deposit by transfer, a letter of credit issued by your bank, or a documentary collection. The method decides when you pay and against which documents, and therefore how much protection you have. See paying foreign suppliers safely.
Phase 3: production, inspection and shipping
Step 7. Follow production and inspect before shipment
Ask for progress reports and photographs, and check the goods before they leave: an independent inspection for consumer goods, a factory acceptance test for machinery. A defect found in the supplier's factory is fixed at the supplier's cost; found in your warehouse, it is your problem. See pre-shipment inspection.
Step 8. Book the freight and insure the cargo
Under E and F terms, you book the main carriage through your forwarder and give the supplier the booking details and cut-off dates. Under C terms the supplier books, but you should still know the carrier and the expected arrival. Insure the cargo yourself whenever the Incoterm does not oblige the seller to do so, and check the cover when it does: under CIF the seller only has to provide minimum cover.
Step 9. Check the documents before they become final
Ask for drafts of the commercial invoice, packing list, bill of lading and certificate of origin, and check them against the contract, the domiciliation file and each other: names, descriptions, HS codes, quantities, weights, values, Incoterm. Under a letter of credit, the documents must also comply with the credit, and your bank will check them.
Phase 4: arrival, clearance and delivery
Step 10. Prepare clearance before the vessel arrives
Send the documents to your customs broker as soon as the goods sail. The broker prepares the declaration, and you file any border-control request, such as a conformity, sanitary or phytosanitary control, so that it can start when the goods arrive. Watch the free time granted by the shipping line: once it expires, demurrage runs every day.
Step 11. Clear, collect and inspect on arrival
Obtain the delivery order from the carrier's agent against the original bill of lading and payment of local charges, pay duties and taxes, and collect the goods once customs grants release. Check them on arrival: note any damage on the delivery receipt, photograph it, and notify the carrier and the insurer within the time limits.
Step 12. Pay the balance and close the file
Pay any balance due under the contract, settle the domiciliation file with your bank where your country requires it, return empty containers on time, and compare the actual costs with your estimate. This comparison is what makes your next landed-cost calculation accurate.
Worked example: a filling machine from Italy to Béjaïa
| Date | Step | Who acts | Output |
|---|---|---|---|
| 5 to 20 January 2027 | Specifications, three quotes compared on landed cost | Dairy | Supplier chosen |
| 1 February | Contract signed, proforma issued | Both parties | Contract |
| 3 February | Domiciliation file filed with the bank | Dairy | Domiciliation number |
| 8 February | Letter of credit issued | Dairy's bank | L/C advised to the supplier |
| 8 February to 10 May | Manufacturing, progress photos every two weeks | Supplier | Progress reports |
| 11 to 12 May | Factory acceptance test with the dairy's engineer | Both parties | Signed FAT report |
| 14 May | Containers loaded at Parma, handed to the carrier | Supplier, forwarder | FCA delivery |
| 18 May | Vessel sails from Genoa; B/L dated after domiciliation | Carrier | Bill of lading |
| 21 May | Documents presented and paid under the L/C | Banks | Payment |
| about 28 May | Arrival in Béjaïa, declaration lodged | Broker | Declaration |
| early June | Release, delivery to the plant, installation | Broker, supplier's technician | Goods on site |
| June | Costs reconciled, file closed | Dairy, bank | Closed file |
Why FCA at the plant? The dairy's forwarder collects the containers, so the dairy controls the carrier, the sailing and the destination charges, and the risk passes when the loaded containers are handed over at the plant. Because the letter of credit calls for an on-board bill of lading, the contract uses the FCA option by which the buyer instructs its carrier to issue one to the seller. The FAT report in the letter of credit means the bank pays only if the machine has passed the test.
Who does what in an import?
| Task | Importer | Supplier | Forwarder | Customs broker | Banks |
|---|---|---|---|---|---|
| Specifications, contract | Leads | Confirms | |||
| Domiciliation, payment | Files, instructs | Domicile, issue the L/C, pay | |||
| Production, inspection | Inspects or appoints inspector | Produces, corrects | |||
| Main carriage under FCA/FOB | Instructs | Delivers to the carrier | Books, coordinates | ||
| Documents | Checks drafts | Issues invoice, packing list, origin | Obtains B/L | Check under L/C | |
| Clearance, delivery | Pays duties, collects | Delivery order | Lodges declaration |
Common mistakes in the import process
- Negotiating before checking the tariff and controls. The surprise comes at the border, when nothing can be changed.
- Letting the supplier ship before the formalities are done. In Algeria, an import shipped before domiciliation can no longer be domiciled, except in duly justified cases authorised under the regulations.
- Paying the full amount before inspection. Once paid, you have little leverage to obtain corrections.
- Buying CIF by default. You lose control of the carrier, transit time and destination charges.
- Waiting for the vessel to arrive before preparing clearance. Free time is short, and controls take time.
- Not reconciling costs. Without comparing estimates and actuals, the next quotation repeats the same errors.
Putting it into practice
On Incoforms, each import is a shipment that records the supplier and the other parties, the ports, the Incoterm and the goods with their HS codes, quantities and weights. The trade documents are generated from that one record, the costing holds every cost category as an estimate and then an actual to produce the landed cost and the margin, and the amounts owed to the supplier are followed in Finance & debts with their due dates and partial payments.
Frequently asked questions
What are the steps to import goods from another country?
Classify the product and check duties and import rules, find and check a supplier, compare quotes on landed cost, sign the contract, complete home-country formalities such as bank domiciliation, set up the payment, inspect the goods before shipment, book freight and insurance if your Incoterm requires it, check the documents, clear customs, collect and inspect the goods, then pay the balance and reconcile the costs.
How long does it take to import goods by sea?
From signed contract to goods in your warehouse, count production time (two to twelve weeks depending on the product), one to two weeks for inspection, booking and loading, the sea transit (a few days within the Mediterranean, four to seven weeks from China), and a few days to several weeks for clearance and controls at destination. Plan backwards from the date you need the goods.
Which documents do I need to import goods?
The core set is the commercial invoice, the packing list, the transport document (bill of lading, air waybill or CMR) and the import customs declaration lodged by you or your customs broker. Depending on the product and country, you may also need a certificate of origin, a conformity, phytosanitary or health certificate, an inspection certificate, an insurance certificate and proof of bank domiciliation.
Do I need a customs broker to import?
In most countries an importer may declare its own goods, but in practice the declaration is usually lodged by a licensed customs broker who knows the national system, the tariff and the controls. You remain responsible for the accuracy of the information, so give the broker complete and consistent documents.